Every line has a MicroLink owner and needs a Vertiv counterpart. Reply to Nick Searra with one name against each.
Block one is two 50 MW OneCore blocks, 100 MW, then the full 250 MW campus block. The host is already energised, so no substation and no grid queue. The Vertiv factory slot is the critical path.
Each track proves something the block cannot afford to learn at scale. The 800 V DC pilot has the hard deadline.
The Vertiv designs are the starting point. MicroLink adds the third loop, the 800 V DC train and the live plant assembly method.