01 · The next ninety days · development, design and quoting
Every line has a MicroLink owner and needs a Vertiv counterpart. Reply to Nick Searra with one name against each.
Joint engineering
Commercial
MicroLink internal
Vertiv input required
02 · First 250 MW block · contract to first energised MW
The host partner is already energised, so no substation and no grid queue. The Vertiv factory slot is the critical path.
Gate, blocks everything downstream
Vertiv scope
MicroLink scope
Joint
03 · Pilots and other solutions · Edge, Pod, 800 V DC and thermal
Each track proves something the block cannot afford to learn at scale. The 800 V DC pilot has the hard deadline.
800 V DC
Thermal and heat recovery
Edge A, 50 kW
Pod, 1.5 MW
04 · Reference designs · the MicroLink design set, issued for construction
The Vertiv designs are the starting point. MicroLink adds the third loop, the 800 V DC train and the live plant assembly method.
Basis of design
Vertiv reference design
MicroLink variant
Issued for construction